REFERENCEs


Replacement of Vecoplan by Melkin

The cement plant underwent modernization involving the replacement of two Vecoplan scrapers with new Melkin units while the plant remained fully operational. The project included the dismantling of the original equipment, the fabrication and installation of frames for the lifting units, the installation of the new equipment—including the lifting units—and the reinforcement of the roof structure and steel floor. 

Date: October 2025 - March 2026
Category: Technology, Machinery and Equipment 
Destination country: Mokrá Cement Plant, Czech Republic

Manufacture of pneumatic conveying components

Manufacture of pneumatic conveying systems and their components for biomass feeding in shaft furnaces.

Date: August 2025 - September 2025
Category: Technology, Machinery and Equipment 
Destination country: Doboj, Bosnia and Herzegovina

Biomass Piping Design

Design and manufacture of pneumatic conveying systems and their components for feeding biomass into a shaft furnace.

Date: November 2025 - March 2026
Category: Technology, Machinery and Equipment 
Destination country: Carmouse Slavec, Slovak Republic

Transfer of Ground Slag and Fly Ash Storage Silos

For the HM plant in Mokrá, we carried out the manufacture, delivery, and installation of process equipment for the modification of storage and transport of ground slag and fly ash between storage silos with capacities of 1,100 m³ and 2,500 m³. The project included the construction of a new conveyor route from the elevator to the 2,500 m³ silo, reconnecting the discharge from the elevator suction filter back to the elevators, a new outlet into the chute for ground slag, modifications to the elevator discharge from the 1,100 m³ silo into the fly ash chute for the hoppers in the cement mill, and a new discharge of fly ash into the original slag silo.

Date: March 2026
Category: Technology, Machinery and Equipment 
Destination country: Mokrá Cement Plant, Czech Republic

CBSN NEW MILL

For the new vertical mill project, we supplied mechanical conveying components and related process equipment. The project included the manufacture and delivery of 9 screw conveyors, a belt conveyor, rotary feeders, slide gates, diverter flaps, and a sampling station.

The equipment was manufactured by RoJa - Consult, while engineering and technical supervision were provided by the MELKOV team.

Date: February 2025 - May 2026
Category: Technology, Machinery and Equipment 
Destination country: Čertovy schody Lime Plant, Czech Republic

Modernization of a Double-Chamber Regenerative Kiln

The original equipment was dismantled and a new system was installed—from the storage silo through the feeding equipment to the burner tubes of the lime kiln. The scope of work included the manufacture and installation of more than 1.2 km of pneumatic conveying lines, including all necessary piping components. In addition, control and shut-off elements (ball valves, gate valves, rotary feeders) were installed, and a biomass combustion system was implemented as an environmentally friendly alternative to conventional fuels.

Date: January 2025 - September 2025
Category: Technology, Machinery and Equipment 
Destination country: Vitošov Lime Plant, Czech Republic

Alternative Fuel Bottling Plant

Construction of a piping system to bottle fuel oil and alternative fuels into the rotary kiln and storage tank. Construction of a boiler house with steam generators and a double-skin storage tank, including a heating system and a shelter for the bottling of fuel oil and AP from tankers. The project also included paving all areas for the operation and maintenance of the site.

Date: January 2024 - March 2025
Category: Technology, Machinery and Equipment 
Destination country: Cement Plant Mokrá, Czech Republic

Replacement of part of the furnace shell

For the replacement of the furnace shell, the production documentation was prepared, the individual parts were delivered and then assembled.

Date: September - October 2024
Category: Technology, Machinery and Equipment 
Destination country: Vápenka Čertovy schody, Tmaň, Czech Republic

shaft kiln Fmr  LOCKSMITH WORK

Part of the locksmith work of the FMR furnace was the replacement of damaged brackets inside the furnace shafts, as well as the replacement of parts of the furnace casing

Furthermore, for ignition burners, the replacement of rectangular boxes with round ones.

Date: October 2023
Category: Technology, Machinery and Equipment 
Destination country: Czech Republic

cement Mill shell                 section replacement

The replacement of the mill shell required shifting of the partition wall, which was located at the place of the mill shell replacement.

Date: December 2022 - January 2023
Category: Technology, Machinery and Equipment    
Destination country: Lafarge Zementwerke, Mannersdorf, Austria

supply, installation of unloading, storage and dosing of cement production equipment

Melkov was general contractor for the installation, storage and dosing of cement production equipment.

Date: January - April 2022  
Category: Technology, Machinery and Equipment
Destination country: Czech Republic

mixing centre

As a part of the reconstruction of the mixing center at the CEMEX Prachovice site, Melkov acted as the general contractor for the reconstruction of the existing Georoc mixing line. The complex delivery consisted in the development of implementation documentation, construction works, production and assembly of new technology and electrical parts, including the schedule and organization of the technological progress of the works.

Date: January - February 2022 
Category: Technology, Machinery and Equipment
Destination country: Czech Republic

RECONSTRUCTION OF THE CLINKER COOLER                            

Reconstruction of the clinker cooler in the Českomoravský cement plant in Mokrá was carried out. As part of the project, MELKOV provided disassembly of the old clinker cooler, manufacture and subsequent installation of a new cooler.

Date: January - February 2021 
Category: Technology, Machinery and Equipment
Destination country: Czech Republic

aeration of the homogenization silo

At the Českomoravský cement plant in Mokrá, the homogenisation forces were reconstructed. As part of this project, Melkov provided the dismantling of the existing clarification troughs, including air distribution. The manufacture and subsequent installation of new settling tanks including air piping was carried out.

Date: December 2020 - January 2021   
Category: Technology, Machinery and Equipment 
Destination country: Czech Republic  

cement cooler     

A cement cooler was installed in the Mokrá plant of Českomoravský cement. The production and subsequent assembly of the cooler was carried out, including the production and assembly of the pneumatic repair.

Date: November - December 2020 
Category: Technology, Machinery and Equipment
Destination country: Czech Republic                                   

wreath gear cover

Design, supply and assembly of the wreath gear cover. Delivered in sections. Implementation including the installation of pressure lubrication of the wreath gear. An adjustment brush seal was used.

Date:January 2020
Category: Technology, Machinery and Equipment
Destination country: Czech Republic

bell seal of the shaft kiln

At the turn of June and July, our fitters installed a new bell seal of the shaft kiln in the Prosenický cukrovar. As a part of this project, MELKOV designed, manufactured and delivered a steel bell seal, including construction works, surface treatment and actual assembly at the cucstomer´s site.

Datum: July 2020 
Category: Technology, Machinery and Equipment 
Destination country: Czech Republic